What is this Project about?
The Terms of Reference Road Map
- 1Step 1
Consult and engage with Indigenous communities, the public and government agencies in order to help Webequie prepare the Draft ToR document
- 2Step 2
Provide the Draft ToR to Indigenous communities, the public and government agencies to review and provide comments (30-day review period)
- 3Step 3
Incorporate comments and input on the Draft ToR from Indigenous communities, the public and government agencies into the Final ToR
- 4Step 4
Submit the Final ToR to the Ministry of Environment, Conservation and Parks (MECP) for review
The Final ToR will be made available to Indigenous communities, the public and government agencies to provide input during the 30-day review period
- 5Step 5
Based on input recieved the MECP will make a decision as whether to approve the Final ToR
The Terms of Reference (ToR) describes how the EA will be prepared, what will be studied, and how Indigenous communities, the public, and government will be consulted during the EA.